Bus shelter construction: Longstaff Court/Andersons Creek Road, Doncaster East

Published
14 Dec 2023
Liveable Places and Spaces Doncaster East
Share

One of the ways we’re building a better Manningham is by improving our bus stops to increase the use of public transport.

This upgrade will make it easier to access the bus stop. It will also include a new shelter, which will give commuters a safe place to wait, no matter the weather.

 

Where is it? 

This is the Longstaff Court/Andersons Creek Road bus stop. It’s on Andersons Creek Road across from 1 Longstaff Court in Doncaster East.

Map locating bus stop at Longstaff Court

 

When will the works happen?

These works will likely occur in the first half of 2024, pending weather and contractor availability. 

The project will be delivered in two phases:

  • Phase one: Civil works (footpaths/landings/ shelter foundations etc.,). This usually takes three to five days.
  • Phase two: Shelter installation. This usually takes one to two days.

 

How will the works affect me?

During the works, commuters will need to use an alternative bus stop. Once phase one is complete, the bus stop will reopen for around a month. Then, it will close again for two days during phase two, to install the shelter. 

We will make every effort to minimise disruptions during construction.

 

Questions?

Contact us if you have any questions about this project or our other bus stop upgrades.

Find out about other bus stop and shelter construction projects.