Footpath and pedestrian crossing construction: Foote Street, Templestowe (Ruffey Creek Trail)

Published
1 Mar 2024
Liveable Places and Spaces Templestowe
Share

Connecting our community through safe footpaths is one of the ways we’re building a better Manningham.

As part of our 2023/24 Capital Works Program, we’re improving the footpath connection for Ruffey Creek Trail at Foote Street, Templestowe.

The works will involve:

  • relocating the current crossing to the eastern side of the intersection 
  • installing pedestrian-operated signals, traffic island fencing, road markings and signage. 
  • footpath widening 
  • upgrades to street lighting. 

 

Where is it?

We are upgrading the pedestrian crossing at the Foote Street and McLachlan Street intersection. Works will occur on Foote Street and the footpaths of Foote Street, McLachlan Street and Ruffey Creek Trail. 

Map of Foote Street Templestowe, where the construction works will occur

Why are these works needed?

These works will create a safer and more accessible footpath connection for pedestrians and Ruffey Creek Trail users. 

 

When will the works happen?

Works are scheduled to begin in March and will likely be completed in July 2024, subject to weather conditions. 

 

How will the works affect me?

Construction works will occur on weekdays, between 7.00am and 5.00pm. You may notice construction noise, footpath closures and minor traffic delays during these times. To complete the works safely, we’ll need to close one lane of Foote Street. We don’t anticipate any disruption to property access.

We will have traffic management and signage on site to guide you through the area. 

We appreciate your patience and understanding while we work to improve the footpath connections in your area.

 

Questions?

Please contact us if you have any questions about these works or our footpaths program.